Insights · Build · September 14, 2026 · 8 min read
A good used machine is a third the price of new. A bad one is a new machine's price spread across two years of downtime. How to tell them apart before you wire the money.
Our first instinct on almost every project is to ask whether a used machine can do the job. Not because we're cheap — because the math is usually overwhelming. A used filler at $60K that needs $25K of integration is $85K against $250K new, and it's available in three weeks instead of twenty. We've built entire first lines this way, and we've bought and resold equipment ourselves.
We've also watched used equipment destroy a production schedule. Here's how we tell the difference.
Purchase price is usually a third to half of the total. Add, honestly:
| Item | Typical range | Often forgotten? |
|---|---|---|
| Rigging, freight, unloading | $3K–$25K | Sometimes |
| Inspection trip and pre-purchase evaluation | $1K–$4K | Usually |
| Controls retrofit or reprogramming | $0–$60K | Almost always |
| Change parts and tooling for your product | $2K–$40K | Usually |
| Guarding, safety circuit, e-stops to current standard | $3K–$20K | Almost always |
| Integration — conveyors, transfers, utilities | $10K–$100K | Sometimes |
| Commissioning and operator training | $5K–$25K | Usually |
| First-year corrective maintenance | 5–10% of purchase | Always |
Run that table before comparing to new. Used still wins most of the time — but by less than the sticker suggests, and sometimes not at all.
A used-equipment dealer is selling as-is; that's the price. But an integrator who's putting a used machine into your line should stand behind the integration — and the better ones will guarantee performance after they've had it in their shop. When we've resold equipment, we've attached an operational guarantee: a specific rate, over a specific run time, at a specific uptime, verified on your floor within a stated window — or you return it. That structure protects you and forces the integrator to actually evaluate the machine instead of flipping it. Ask for it. If nobody will offer one, that tells you something about the machine.